🔧 Comprehensive Hydraulic Circuit Maintenance – Cifa K56C Concrete Pump 🔧
Is your concrete pump overheating? Or are the boom connections unresponsive? ✋
The problem is often deeper than you think... and it might start with a non-original filter!
📌 Fault Diagnosis:
The Cifa K56C pump arrived with issues in boom connections #1 and #5. After a thorough engineering inspection, the root cause was identified as:
🔸 Use of non-original filters, which led to impurities in the hydraulic circuit.
🔸 Power failure to the ED72 valve (Negative Characteristic Control) for the S-valve pump, causing the pump to remain at maximum angle permanently under charge pressure.
🔸 This resulted in a massive increase in circuit temperature.
🔸 The consequence: failure of the non-original filters and transfer of particles to the piston valves, causing them to malfunction.
✅ Work Performed:
✔ Repaired issues with boom connections #1 and #5, restoring them to efficient operation.
✔ Repaired the cylinder for boom connection #4.
✔ Complete periodic maintenance: Oil change + original filters.
✔ Installed pressure gauges on:
• Main Pumping Circuit A4VG 175EP series 40 x2
• Charge Pump Circuit
• Changeover Circuit A10VO 28 ED72
• Boom Circuit A7VO 55 LRDS
This allows for regular monitoring of the pump's condition and early detection of any faults before they become costly breakdowns 📊
Advice from the Engineers:
A cheap filter can cost you the entire circuit repair. Always use original filters and oils, and install pressure gauges to monitor your pumping equipment.
🏢 Global Hydraulic Power
Specialists in the maintenance and repair of hydraulic systems for concrete and heavy equipment
🌐 www.globalhydraulicpower.com
📞 0559015147 | 0599635314
📲 WhatsApp:
📍 Riyadh – Al Sulay – Exit 17
#مضخة_خرسانة #سيفا #Cifa #K56C #صيانة_هيدروليك #هيدروليك #الرياض #السعودية #معدات_ثقيلة #مضخات_خرسانة #جلوبال_هيدروليك_باور #حراج #صيانة_معدات